TIMELINE (2019-2023):
-
*The following dates are subject to change.
- January 2019
- Site Selection
- Site Selection
- March 2019
- Select Design Firm - Selected Zyscovich Architects to Design Aubrey Rogers High School
- Select Design Firm - Selected Zyscovich Architects to Design Aubrey Rogers High School
- June 2019
- Start Educational Specification Development
- Start Educational Specification Development
- September 2019
- Complete Educational Specification Development
- Start Schematic Design
- February 2020
- Complete Schematic Design
- Start Design Development
- April 2020
- Board Approves Construction Management Firm – Owen-Ames-Kimball Company
- Board Approves Construction Management Firm – Owen-Ames-Kimball Company
- July 2020
- Complete Design
- Complete Design
- April 2021
- Board Approves Preconstruction Services
- Board Approves Guaranteed Maximum Price Contract
- May/June 2021 (Tentative)
- Start Construction
- Start Construction
- August 9, 2022
- Board Presentation for Naming Process
- Board Presentation for Naming Process
- August 18, 2022
- Naming Process Community Meeting @ NNM (6:00 – 7:00 PM)
- Naming Process Community Meeting @ NNM (6:00 – 7:00 PM)
- August 19, 2022
- Naming Survey 10-day Window
- Naming Survey 10-day Window
- September 12, 2022
- Board Meeting – Naming of High School & Review Boundary Modification Timeline/Process
- Board Meeting – Naming of High School & Review Boundary Modification Timeline/Process
- November 2022 (Tentative)
- Boundary Modification Community Meetings
- December 2022 (Tentative)
- Board Meeting – Identify Boundary Modification Scenario
- Board Meeting – Identify Boundary Modification Scenario
- August 2023
- Open School
- January 2019