TIMELINE (2019-2023):

  •  *The following dates are subject to change.

    • January 2019
      • Site Selection

    • March 2019 
      • Select Design Firm - Selected Zyscovich Architects to Design GGG

    • June 2019 
      • Start Educational Specification Development

    • September 2019
      • Complete Educational Specification Development
      • Start Schematic Design

    • February 2020
      • Complete Schematic Design
      • Start Design Development

    • April 2020
      • Board Approves Construction Management Firm – Owen-Ames-Kimball Company 

    • July 2020 
      • Complete Design

    • April 2021 
      • Board Approves Preconstruction Services
      • Board Approves Guaranteed Maximum Price Contract

    • May/June 2021 (Tentative)
      • Start Construction

    • September 2022 (Tentative)
      • School Naming

    • November 2022 (Tentative)
      • Rezoning Community Meetings

    • December 2022 (Tentative)
      • Rezoning Approval by School Board

    • August 2023
      • Open School